IN Brief:
- London Gateway Port Limited has selected Trackwork for phase two of its second rail terminal.
- The contract is valued at £30,999,487 excluding VAT and includes five sidings, 21 switches and crossings, and an approximately 850-metre crane rail beam.
- The procurement standstill is due to end on 3 December, with contract commencement expected on 4 December.
London Gateway Port Limited has selected Trackwork for the second construction phase of its additional rail terminal, advancing the expansion of inland freight infrastructure at the DP World-operated Thames container port. The contract is valued at £30,999,487 excluding VAT and covers railway construction, civil engineering, signalling, telecommunications, and electrical works.
The procurement notice identifies 4 December 2026 as the expected start of the contract, with completion scheduled for 19 March 2028. The procurement remains within its standstill period, which is due to end on 3 December. The planned timetable therefore concerns a selected contractor rather than construction already under way.
Trackwork’s scope includes five new sidings, numbered seven to eleven, alongside two tracks numbered twelve and thirteen that were completed during earlier development phases and are already operating. The new infrastructure requires 21 switches and crossings to connect it with the existing railway layout.
The civil engineering package also includes an approximately 850-metre reinforced concrete crane rail beam supported by piled foundations. Earthworks, drainage, utility diversions, access routes, and cable infrastructure form part of the construction requirements. The beam will provide a structural interface for rail-mounted handling machinery, with its alignment and foundation design required to accommodate the concentrated and moving loads imposed by the equipment.
Rail terminals link the port’s container handling operation with scheduled inland freight services. Containers discharged from a maritime vessel are moved to storage positions before being allocated to their onward transport. Those destined for rail must be transferred to a loading area where handling equipment can place them onto wagons according to the train’s configuration and destination.
A train may occupy terminal infrastructure during arrival, loading, unloading, and preparation for departure. Providing more sidings gives the operator greater flexibility to position trains without requiring every activity to use the same tracks. The effective increase in capacity will also depend on train lengths, handling rates, and the availability of paths through the wider railway network.
Switches and crossings provide the connections that allow trains to move between the arrival, handling, and departure sections of the terminal. Integrating five new sidings requires changes to the routes that can be established within the existing railway layout, alongside signalling arrangements to ensure that conflicting movements cannot be authorised simultaneously.
Trackwork’s contract covers new and relocated signalling equipment, a new shunters’ cabin, an updated control panel, train detection infrastructure, and integration with existing control systems. The electrical package also includes supplies for the new equipment and points heating, which helps keep switches operational in freezing conditions. Telecommunications and CCTV equipment are included in the wider interface works.
Construction will need to be sequenced around the port’s existing operations. The connection of new track, power, and signalling infrastructure to working systems can require planned periods when individual sections are unavailable. Staged installation and testing can limit the effect on freight services while ensuring that new infrastructure is integrated before it is released for use.
London Gateway handled more than three million TEU during 2025, according to DP World, following the introduction of its fourth berth and additional vessel calls from the Gemini Cooperation’s Asia–Europe services. The second rail terminal entered operation during that year, with the current procurement extending the initial development rather than creating its first operating tracks.
The port’s wider £1bn investment programme includes two additional deepwater berths alongside the expansion of rail capacity. Additional maritime services can increase the volume of cargo requiring inland transportation, with the relative availability of road and railway connections influencing how that freight is distributed through Britain.
At Southampton, DP World has already introduced commercial measures to encourage more use of railway services. Its modal shift programme has supported additional rail container movements, including the use of incentives for eligible freight flows. The London Gateway investment addresses the physical infrastructure needed to accommodate more train operations as demand develops.
The number of sidings alone does not determine the amount of additional freight that can travel by rail. Operators also require suitable wagons, locomotives, train paths, and connections with inland terminals serving cargo owners. The new engineering works provide infrastructure for those services, but the procurement notice does not quantify the resulting annual container throughput. Subject to contract commencement in December, the phase is scheduled to run into March 2028, when the installation and integration programme is due to be completed.