Rotterdam prepares 1.4m TEU terminal expansion

Rotterdam prepares 1.4m TEU terminal expansion

Rotterdam is preparing another major expansion of its container infrastructure. APM Terminals Maasvlakte II could gain 1.4 million TEU of annual capacity through 711 metres of additional quay and 25 hectares of terminal space.


IN Brief:

  • APM Terminals and the Port of Rotterdam Authority are preparing another expansion of Maasvlakte II.
  • The project includes 711 metres of quay, 428 metres of landside crane rail, and 25 hectares of terminal space.
  • Construction is provisionally scheduled between October 2027 and January 2030, subject to investment approval.

APM Terminals and the Port of Rotterdam Authority are preparing a further expansion of Maasvlakte II, targeting an increase of approximately 1.4 million twenty-foot equivalent units (TEU) in annual container handling capacity. The proposed development would extend the existing terminal at Prinses Amaliahaven by 25 hectares and provide approximately 711 metres of additional quay.

The port authority will prepare the land and deliver maritime infrastructure, including the quay wall, an extension of 428 metres to the landside crane rail, and dredging of around 1.3 million cubic metres of sand. APM Terminals will concentrate on the development of terminal operations. The first part of an existing expansion programme has recently entered service, with the next phase to be undertaken while the established terminal continues operating.

The development remains subject to investment approval. The port authority’s supervisory board is expected to consider the proposal in December, followed by its shareholders in February 2027. The pre-selection process for contractors is scheduled for publication on TenderNed in January, with the quay wall tender award phase expected to begin in March. Construction is provisionally scheduled to take place between October 2027 and January 2030.

Additional quay length would allow the operator to accommodate more deepsea, feeder, and inland shipping services. Large container vessels require sufficient contiguous berth space to position several cranes alongside their cargo holds. Smaller vessels require less quay length individually but can make more frequent calls, so berth allocation must also account for the time each ship is expected to occupy the infrastructure.

The extension of the crane rail is a separate part of the engineering scope. Rail-mounted ship-to-shore cranes impose substantial concentrated loads on quay structures, which must be designed to accommodate the equipment’s movement, lifting loads, and alignment tolerances. Extending the rail provides a physical interface through which crane operations can be developed along the expanded berth. The parties have not yet published the equipment procurement specification or number of additional cranes.

Maasvlakte II already uses automated guided vehicles to transfer containers between the quay and storage yard, with remotely operated quay cranes and electrified handling equipment. The terminal’s automation arrangements allow individual container movements to be scheduled against the requirements of incoming and outgoing vessels and the available storage positions.

A large container ship can generate thousands of individual handling movements during one port call. The rate at which its cranes can discharge containers depends partly on whether the horizontal transport equipment can remove each unit from the quay and deliver it to the correct yard position. Where the yard is congested, cranes may have to wait for transport equipment or storage availability, extending the vessel’s turnaround time.

The additional 25 hectares provide space in which the operator can develop more landside handling capacity. Its eventual configuration will influence the number of containers that can be stored, the accessibility of individual units, and the distance that automated vehicles must travel. Increasing storage density can make more efficient use of the available land, but retrieving a container positioned beneath other units may require additional movements.

Yard planning must distinguish between cargo awaiting collection by road, containers scheduled for rail or barge services, and units being transferred to another maritime vessel. Grouping stock according to onward movements can reduce unnecessary repositioning, provided that information about collection and departure schedules remains sufficiently accurate.

Rotterdam’s rail and inland waterway connections enable container movements to reach distribution and manufacturing centres across continental Europe. Expanding maritime capacity increases the importance of coordinating terminal handling with inland service schedules, particularly where several large vessels arrive within a relatively short period. More quay capacity can otherwise transfer pressure into the terminal yard and onward transport interfaces.

The investment also follows a change in the terminal’s ownership structure, with Hapag-Lloyd completing its purchase of a 25% interest in Maasvlakte II earlier in November. Shipping line ownership provides a direct commercial relationship with a terminal’s long-term investment, although the latest infrastructure proposal remains a separate development subject to the port authority’s approval process.

Construction within an operating automated terminal requires interfaces between marine engineering, electrical infrastructure, crane installation, and the systems used to coordinate equipment movements. Work areas need to be separated from existing commercial activity, with commissioning planned around the availability of the new berth and yard infrastructure. The projected 1.4 million TEU increase refers to annual capacity after completion, not an immediate increase in Rotterdam’s handled volumes. The December investment review and January contractor pre-selection are the next scheduled milestones.


Stories for you


  • Achilles launches contractor compliance automation platform

    Achilles launches contractor compliance automation platform

    Achilles has launched Site Control to automate contractor compliance management. The platform combines AI-supported document checks and specialist assessment with records covering workers, vehicles, plant, and machinery.


  • London Gateway selects rail terminal contractor

    London Gateway selects rail terminal contractor

    London Gateway has selected Trackwork to expand its rail terminal. The proposed £31m contract covers five additional sidings, signalling infrastructure, and civil engineering works, with commencement expected in December.