Philippines advances Matnog port expansion works

Philippines advances Matnog port expansion works

Philippine authorities have authorised preparatory works at Matnog ferry port. A ₱2.195bn contract has been signed for the expansion programme, which is intended to provide additional operating space and roll-on/roll-off infrastructure at a congested inter-island freight gateway.


IN Brief:

  • The Philippine Ports Authority has awarded a ₱2.195bn expansion contract to a joint venture between Khan Ko Chi Construction and Development Corporation and SB Construction Corporation.
  • The programme begins with site clearance, removal, disposal, and excavation, ahead of planned operating-area and RoRo ramp construction.
  • The notice to proceed is dated 9 November, with project delivery reported against a 900-calendar-day period.

The Philippine Ports Authority (PPA) has awarded a ₱2.195bn contract for the Matnog Port Expansion Project in Sorsogon, advancing work at a major roll-on/roll-off freight gateway connecting Luzon with the Visayas and Mindanao. The contract and notice to proceed are dated 9 November 2026, following the authority’s decision to select a joint venture between Khan Ko Chi Construction and Development Corporation and SB Construction Corporation.

The procurement concerns the first phase of the port expansion programme, with works beginning through site clearance, removal, disposal, and excavation. The wider development provides for additional port operating areas and continuous roll-on/roll-off (RoRo) ramp infrastructure in subsequent construction phases. These elements are intended to improve the handling of vehicles and associated freight at a crossing that has experienced recurring congestion and extensive truck queues.

The PPA’s Bids and Awards Committee recommended the successful joint venture on 21 October after assessing the competing submissions. The formal notice of award followed on 27 October, with the contract signed on 9 November. The authority’s procurement record gives the project cost as ₱2,194,911,479.18, representing a substantial investment in the development of Matnog’s port infrastructure.

The successful contractor was selected through a competitive process on the basis of its responsive bid. Procurement reporting identifies a 900-calendar-day delivery period, although the precise sequencing of individual construction activities will depend on the approved programme. The authority has not published a revised opening date for the proposed additional RoRo facilities or a quantified increase in the number of vehicles that the completed development will accommodate.

Matnog occupies a critical position on the Philippines’ eastern inter-island freight corridor. Located at the southern end of Luzon, the port provides ferry connections across the San Bernardino Strait to Northern Samar. Cargo vehicles can then continue through the Visayas towards other domestic markets, including Mindanao, using a combination of road transport, bridges, and further ferry services.

The route is used by commercial vehicles carrying goods between the country’s principal island groups. Freight movements must be coordinated with ferry schedules, loading arrangements, and road access at both ends of the crossing. Delays at Matnog can extend the journey time for vehicles that have already travelled substantial distances overland, affecting the delivery of goods to distribution centres, industrial facilities, and other customers.

Roll-on/roll-off services differ from conventional container terminal operations because suitable vehicles and trailers move directly onto vessels through loading ramps. Cargo can remain aboard the vehicle or trailer during the crossing, avoiding the need for every consignment to be transferred by quay crane. The operating capacity of a RoRo port consequently depends on the interaction between its ramps, vehicle holding areas, ferry availability, and the road network supplying arriving traffic.

Vehicle holding space is an important part of that arrangement. Trucks and passenger vehicles may arrive ahead of their allocated sailing and require space to wait while loading operations are organised. When the number of vehicles exceeds the available holding capacity, queues can extend beyond the terminal and occupy roads approaching the port. Additional operating areas can provide greater flexibility in managing these movements, provided the terminal’s internal road layout and loading facilities are developed to accommodate them.

Ramp infrastructure creates another capacity constraint. Ferry operators need access to loading points compatible with their vessels and the vehicles they carry. The time required to embark and disembark freight can affect vessel turnaround, particularly where heavy goods vehicles compete for limited space with buses and passenger cars. A continuous RoRo ramp can form part of an improved operating arrangement, although actual throughput will depend on its design and the number of vessels available to use it.

The Matnog expansion programme addresses both land-side operating space and maritime loading infrastructure. Initial removal and excavation activities are required before the subsequent facilities can be constructed in accordance with the approved design. Site preparation must account for the conditions of the existing terminal, the intended new working areas, and the need to maintain safe construction activity close to an operating ferry gateway.

Construction within an active port requires coordination between contractors, terminal managers, ferry operators, and the authorities responsible for transport access. Working areas must be separated from vehicle routes where appropriate, and temporary changes to circulation arrangements may be required as individual sections of the project progress. The publicly available contract information does not establish the precise traffic management arrangements or the extent to which existing operations may be affected during construction.

Congestion at Matnog has been a recurring problem, especially during holiday periods when passenger demand increases alongside commercial vehicle movements. Long truck queues have been reported on roads approaching the terminal, while port and maritime authorities have examined measures intended to improve the coordination of ferry operations and vehicle access. Demand can change sharply during these periods, making the availability of terminal space and reliable sailing schedules important to the movement of commercial freight.

The capacity of the wider crossing is also influenced by facilities on the Samar side. An increase in departures from Matnog cannot deliver its full benefit if receiving ports lack the ramp capacity, vehicle holding areas, or road connections needed to process arriving traffic. Philippine transport authorities have consequently examined port infrastructure on both sides of the route, recognising the need to coordinate improvements across the inter-island network.

The current development follows earlier investment at Matnog. In 2024, the PPA awarded a separate contract valued at approximately ₱487.8m for expansion work at the Sorsogon RoRo terminal. That earlier award formed part of the authority’s continuing efforts to improve freight and passenger handling in the area. The newly awarded ₱2.195bn programme is a distinct procurement action and should not be treated as an increase in the value of the previous contract.

Freight operators using the crossing face costs associated with waiting time, vehicle availability, and changes to delivery schedules. A truck held in a queue cannot complete the next stage of its planned journey, while prolonged delays can disrupt subsequent collections or deliveries. The economic effect depends on the type of cargo, the vehicle’s operating arrangements, and the availability of alternatives. The PPA has not published a quantified assessment of the freight cost reductions expected from the new infrastructure.

The design of the operating areas will influence how effectively the additional space can be used. Separate arrangements for arriving and departing vehicles can help avoid conflicting movements, while appropriate queue management and access to loading ramps are needed to maintain orderly traffic flows. These are operational considerations for the planned expansion, not confirmed specifications or performance outcomes for the construction work now authorised.

Ferry availability remains a separate constraint. Even with additional port space, the number of vehicles crossing the strait depends on the frequency and capacity of the vessels providing the service. Weather conditions, maintenance requirements, and loading procedures can also affect the number of completed sailings. Improved terminal infrastructure can support more reliable handling of vehicles, but cannot independently eliminate every cause of delay along the route.

The confirmed advance is the award and commencement authorisation for the Matnog expansion programme, with site preparation forming its initial construction stage. Additional operating areas and ramp infrastructure will follow through the planned development sequence, subject to implementation of the remaining works. The project provides a substantial new investment at a strategic inter-island freight connection, with its eventual capacity and operating performance still to be established.


Stories for you


  • Manufacturers increase stockpiles as supply concerns persist

    Manufacturers increase stockpiles as supply concerns persist

    Manufacturers increased precautionary inventories despite easing global supply chain pressure. GEP’s October index shows stronger stockpiling in North America and Europe, continued materials shortages, and rising transportation costs, while UK manufacturers reduced their inventory buffers.


  • London Gateway suspends empty container returns again

    London Gateway suspends empty container returns again

    Maersk has suspended empty container acceptance at London Gateway again. The restriction began at 08:00 GMT on 11 November, with hauliers directed to check current return instructions before using alternative depots where space and authorisation permit.