Gothenburg installs tank for marine biogas supply

Gothenburg installs tank for marine biogas supply

Nordion Energi has installed Gothenburg’s first major liquefaction plant component. The 500-cubic-metre storage tank will support planned marine and industrial fuel deliveries from 2027.


IN Brief:

  • Nordion Energi has installed a 500m³ liquefied biogas tank at its plant under construction at Gothenburg port.
  • The nearly 140-tonne tank can store up to 200 tonnes of LBG once the facility has been commissioned.
  • The operator targets completion in Q2 2027 and eventual annual supply capacity of 250GWh to shipping, transport and industry.

Nordion Energi has installed a 500-cubic-metre storage tank at its liquefied biogas plant under construction at the Port of Gothenburg. The tank arrived by vessel, weighs nearly 140 tonnes and is designed to hold up to 200 tonnes of fuel once the facility is commissioned. Foundations and base slabs have been completed, but the tank is the first major plant component installed. Nordion Energi, which will own the facility, is targeting completion in the second quarter of 2027; commercial liquefaction has not begun.

The plant is being developed and will be owned by Nordion Energi. It is designed to draw biogas from the western Swedish gas grid and convert it into a liquid suitable for storage and delivery to customers in shipping, heavy transport and industry. The port says this will be Sweden’s first biogas liquefaction plant directly connected to that grid. The connection offers a route for gas from producers elsewhere in the network to reach a concentrated transport fuel market at the port.

Liquefaction makes a given energy quantity of methane more compact for storage and transport than gas at normal pressure, but requires significant cooling, insulation and careful pressure management. At Gothenburg, gas entering from the grid will be processed and held in the new tank before distribution to users with suitable fuel equipment. The tank therefore connects the production and delivery stages rather than operating as a stand-alone fuel depot. Its piping, control systems and safety equipment still need to be integrated and commissioned.

The completed plant is designed to supply 250 gigawatt-hours of liquefied biogas annually. The port compares that quantity with the approximate annual fuel needs of 500 heavy trucks or 50 vessels; those are illustrative consumption equivalents, not signed demand commitments. The port has previously described an output rate of about 50 tonnes a day. Actual production will depend on gas availability, plant operating hours and distribution arrangements once commissioning has been completed.

Biogas can be produced from organic material and upgraded to biomethane, after which it can use gas infrastructure where the required specifications are met. At Gothenburg, grid connectivity is intended to connect supply from Swedish producers with customers able to handle liquefied fuel. The exact emissions benefit compared with conventional marine fuel depends on feedstock, production processes, methane losses, transport, combustion and the accounting method applied. The project information does not provide a verified full lifecycle emissions figure.

A local source of liquefied biogas could make fuel planning easier for vessels operating on gas-capable engines, especially when operators need enough product to bunker during a scheduled port call. Delivery arrangements must match the vessel’s fuel system, the available transfer equipment and the safety requirements of the berth. Fuel availability also depends on upstream biogas procurement and the liquefaction plant’s operating schedule. The installation of the tank does not establish commercial bunker prices or guaranteed volumes for every visiting ship.

Several shipping companies calling regularly at Gothenburg already use liquefied biogas, according to the port, and ST1 Biokraft has reserved part of the proposed plant’s capacity. These arrangements provide an established user and producer base for the development. The port has not published the allocation of the full 250GWh capacity or named all future buyers. Allocation between bunker supply, road transport and industrial customers remains to be determined.

Moving the nearly 140-tonne vessel-delivered tank into position required the foundations to be ready before heavy lifting and mechanical installation could proceed. Connected processing equipment, pipework and controls will have to follow. Commissioning of low-temperature fuel systems includes checking containment, transfer arrangements and safe operating conditions; the installation milestone alone does not establish that the tank can receive product. The heavy storage component is in place, with the connected plant still under construction.

Gothenburg is a major Scandinavian freight gateway handling containers, roll-on/roll-off vehicles, energy products and general cargo. Bunker availability intersects with those operations because vessel turnaround must accommodate cargo handling, pilotage, fuel transfers and safety restrictions. Liquid gas handling can require separation zones and operating procedures that differ from those for conventional fuel oil. The plant therefore becomes part of the port’s wider logistics infrastructure, although the release does not identify changes to individual berth arrangements.

Direct connection to the west Swedish gas grid is intended to create an outlet for domestic biomethane producers without requiring each supplier to transport liquefied fuel to Gothenburg. Producers must still meet the gas network’s quality and injection requirements, and the plant needs reliable deliveries and corresponding commercial agreements. The grid link could broaden the geographic sourcing base for marine fuel, although the operator has not published gas supply volumes or network transport charges.

Remaining work involves the grid interface, processing systems, tank connections, electrical services, control equipment and operational acceptance. A complete commissioning programme must establish that the equipment performs safely before routine deliveries to ships, trucks and industrial customers begin. Nordion Energi continues to target the second quarter of 2027 but has not identified the first commercial bunkering date or published a detailed production ramp-up schedule.

The 500-cubic-metre tank is the first substantial equipment installation at a facility designed to provide 250GWh of liquid renewable gas each year. The plant would connect Swedish grid-supplied biomethane with shipping, road freight and industrial demand from Gothenburg. Its potential supply role is defined; the next measurable steps are completion of the connected processing equipment, commissioning and the first recorded commercial deliveries.


Stories for you


  • Gothenburg installs tank for marine biogas supply

    Gothenburg installs tank for marine biogas supply

    Nordion Energi has installed Gothenburg’s first major liquefaction plant component. The 500-cubic-metre storage tank will support planned marine and industrial fuel deliveries from 2027.


  • Noatum gains 15-year Motril vehicle concession

    Noatum gains 15-year Motril vehicle concession

    Noatum has secured long-term rights for vehicle logistics in Spain. Motril Port Authority approved 79,107 square metres for the existing operation, with an initial fifteen-year concession.